GP or SP? AS/NZS 1554.1 weld categories in plain English
AS/NZS 1554.1 sets two weld quality categories. Which one applies changes the inspection, the rework risk and the paperwork you get at handover — so it belongs on the drawings.
In this article
The short answer
AS/NZS 1554.1 is the Australian standard for welding structural steel. It sets two weld quality categories: GP, general purpose, and SP, structural purpose. SP carries tighter acceptance limits and more inspection. The drawings should say which category applies to which weld. If they do not, ask before the package is priced, because the difference shows up in inspection cost, rework risk and the records handed over at completion.
Every structural weld in Australia is made to a category, whether or not anyone wrote it down. AS/NZS 1554.1 gives two: GP, general purpose, and SP, structural purpose. They are not grades of workmanship so much as grades of scrutiny.
What changes between GP and SP
An SP weld has tighter limits on what is acceptable — the size and number of defects a weld may carry before it has to be cut out and redone — and it attracts more inspection to prove it. A GP weld is made to the same standard of practice, but it is checked against looser acceptance criteria because the consequence of a small imperfection is lower.
The practical effect on your job is threefold: SP welds take longer, they are inspected more, and they carry a higher chance of rework. That is not a reason to avoid SP. It is a reason to specify it where it is needed and not where it is not.
Who decides, and where it should appear
The design engineer decides, and the category belongs on the structural drawings — ideally weld by weld, or at minimum as a general note with the exceptions called out. Where drawings are silent, a fabricator has to assume, and different fabricators will assume differently. That is one of the quieter reasons two quotes for the same steel come back apart.
Procedures and people
Two things sit behind any compliant weld, and they are worth asking about:
- The welding procedure. A qualified procedure sets out the process, consumables, preheat, run sequence and parameters for that joint in that material. It is what makes a weld repeatable rather than a matter of the day.
- The welder. Welders are qualified to weld particular processes, positions and materials. Qualification is not permanent — it has currency, and the records should be current at the time the work is done, not at the time somebody was hired.
If a fabricator cannot put procedure and qualification records in front of you, the weld category on the drawing is decoration.
Inspection: who looks, and who pays
Visual inspection is the base layer and it catches most of what goes wrong. Beyond that, non-destructive testing is used where the drawings or the project's inspection and test plan call for it — magnetic particle testing for surface and near-surface defects, ultrasonic testing for what is inside a full penetration weld.
Three things about testing are worth settling in the subcontract, because they are argued about otherwise: what proportion of welds is tested, who engages and pays the testing authority, and what happens when a test fails — who pays for the rework and the retest.
The timing matters as much as the terms. Testing a weld in the workshop is straightforward. Testing the same weld once it is six metres in the air needs access equipment, a permit and a day nobody planned for.
Site welds are a different animal
Workshop conditions are controlled. Site conditions are not — wind, position, access, moisture and the state of the surface all work against a good weld. Where a connection can be bolted rather than site-welded, bolting is usually the lower-risk answer. Where site welding is required, it needs the same procedure and qualification discipline as shop welding, plus a plan for coating repair afterwards if the steel is galvanised or painted.
What to ask for at handover
- The weld category applied, and to which welds
- Welding procedures used
- Welder qualification records, current at the time of the work
- Inspection records against the inspection and test plan
- Non-destructive testing reports, where testing was called for
- Any non-conformance raised, and how it was closed out
Assembled as the job runs, that pack takes minutes a week. Assembled at the end, it takes days — and by then the people who could answer the questions have moved on to the next job.
Common questions
What does SP mean on a structural drawing?
SP is the structural purpose weld quality category in AS/NZS 1554.1. It applies tighter acceptance limits than the general purpose category, GP, and normally attracts more inspection. Where drawings show SP, the welds are being held to the stricter criteria in the standard.
Is AS/NZS 1554.1 the only welding standard that applies?
It is the main one for welding structural steel. Other parts of the AS/NZS 1554 series cover different situations — stainless steel and welding subject to fatigue loading among them — and AS/NZS 5131 sits alongside as the fabrication and erection standard. The project specification should say which apply.
Who pays for non-destructive testing on a steel package?
Whoever the subcontract says. It is commonly the builder who engages the testing authority, with the fabricator carrying the cost of rework and retesting on any weld that fails. What matters is that it is written down before work starts, along with the proportion of welds to be tested.
Do welders have to be qualified for every job?
Welders hold qualifications for particular processes, positions and materials, and those qualifications have currency requirements. The records should be current for the work being done. Asking to see them before you engage a fabricator takes a minute and tells you a great deal.
Keep reading
More from the workshop
Standards
Construction categories: CC1 to CC4, and which one your steel package needs
AS/NZS 5131 sorts structural steelwork into four construction categories. Naming the wrong one costs you either inspection you never needed, or paperwork that does not exist at handover.
Prequalification
Choosing a steel subcontractor: what to check before you engage
Licences, insurances and welding standards are the easy part. The things that actually go wrong on a steel package are further down the list.