What a steel subcontractor's prequalification pack should contain
Prequalification is where a head contractor decides whether you are worth sending drawings to. Most packs are held up for expired certificates rather than missing ones.
In this article
The short answer
A prequalification pack is the evidence a head contractor needs before letting a steel package: licensing, insurance, safety system, quality system, welding capability, plant and people, financial capacity and referees. The documents themselves are rarely the problem. What holds packs up is currency — an expired insurance certificate or a superseded policy is the most common reason a submission comes back.
Prequalification is the gate before the gate. Before a head contractor sends you a drawing set, somebody in their office decides whether your business is one they can let a package to without creating a problem for themselves. That decision is made on paperwork, usually by someone who has never met you, often in half an hour.
Which means the pack is worth getting right once and keeping current, rather than assembling under time pressure every time.
What they are actually assessing
Three things, in this order: can you legally do the work, will you create risk for us, and can you actually deliver a package this size. Every document in the pack answers one of those.
Licensing and legal
- Company name, ABN and structure, matching the name on the quote
- QBCC licence number and class, current, with the licence holder named
- Any trade licences or registrations relevant to the scope
Get the entity name consistent across every document. A pack where the insurance is in one name, the licence in another and the quote in a third gets queried every time, even when the explanation is simple.
Insurance
- Public and products liability, with the sum insured stated
- Workers compensation
- Plant, tools and motor vehicle cover where relevant
Certificates of currency, not policy schedules, and not expired. This is the single most common hold-up in the whole process. Diarise renewal dates and reissue the pack the week they change.
Safety
- A work health and safety management system, or at minimum a policy plus the procedures behind it
- Safe work method statements for the high risk work in your scope — hot works, working at height, cranes and lifting, confined space
- Incident and injury history
- Site induction and ticket records for the crew: white card, EWP, working at heights, confined space, high risk work licences
A head contractor's safety manager reads this part first and hardest, because it is the part that lands on them if it goes wrong.
Quality, and the welding evidence
This is where most steel packs are thin, and it is the part that separates a fabricator from a general trades business.
- Welding procedures for the processes and joint types you actually run
- Welder qualification records against AS/NZS 1554.1, current, and named
- Who supervises welding, and their qualification
- An inspection and test plan template, showing hold points and who signs them
- Material traceability approach — how a plate on the floor gets tied to a test certificate
- Coating and surface preparation capability, and how thickness is verified
If a builder is letting a structural package, this section is the one that tells them whether your compliance claims survive an audit.
Capability and capacity
- Workshop size, bay capacity, and the plant list — what you can cut, roll, press and lift
- Crane and transport arrangements, and the largest piece you can move
- Crew numbers and supervision structure
- Typical and maximum package value you take on
Be honest about the ceiling. A builder who finds out mid-job that a package was above your capacity will not prequalify you again, and they talk to each other.
Referees and project history
Three to five completed projects of comparable type and value, with a contact who has agreed to take the call. Name the scope and the value band rather than a vague description. If a client will not let you name them, say what the project was without naming it — that is normal and builders understand it.
How we handle it
We keep a current pack ready rather than building one per tender — QBCC 15560197, insurance to twenty million, welder qualifications and procedures on file, and an inspection and test plan template that comes out with the quote rather than after it. If your prequalification portal wants a specific form completed, send it with the drawings and it comes back with them.
Common questions
What is the most common reason a prequalification pack gets rejected?
Expired documents, by a wide margin. Insurance certificates of currency lapse annually and licences renew on their own cycle, so a pack that was complete six months ago is often not complete today. The fix is administrative rather than difficult: diarise every expiry date and reissue the pack the week anything changes.
Do we need a full quality management system to prequalify for steel work?
Not always a certified system, but you do need the evidence behind one. For a structural steel package that means welding procedures, current welder qualification records against AS/NZS 1554.1, a named welding supervisor, an inspection and test plan showing hold points, and a workable approach to material traceability. Some larger head contractors and public sector clients require third party certification on top of that.
How many project referees should we include?
Three to five completed projects of similar type and value is the usual expectation, each with a contact who knows the call is coming. Quality matters more than quantity — one referee at a head contractor who will speak well of you is worth more than a long list of jobs nobody can verify.
Can we list a project if the client will not let us name them?
Yes, and it is common. Describe the project type, the scope and the value band without identifying the client or the site. Builders deal with confidentiality constantly and will not hold it against you. What they will notice is a description so vague it could be any job at all, so keep the scope detail specific even when the name is not.
Keep reading
More from the workshop
Compliance
Choosing a steel subcontractor in Brisbane
What to check before you let a steel package, and which of it actually predicts how the job will run.
Standards
Construction categories: CC1 to CC4, and which one your steel package needs
AS/NZS 5131 sorts structural steelwork into four construction categories. Naming the wrong one costs you either inspection you never needed, or paperwork that does not exist at handover.