Fire-rated steelwork: what the builder has to supply
Fire protection is priced off the fire resistance level, the section sizes and the protection system. If those three are not settled before fabrication, the steel gets blasted twice.
In this article
The short answer
Fire protection on structural steel is set by a fire resistance level nominated against the National Construction Code, and delivered by one of three systems: intumescent coating, board encasement or sprayed material. The fabricator needs the FRL, the member sizes and the named protection system before pricing, because all three change the surface preparation, the primer and the order the work has to happen in.
Fire protection is the part of a steel package that arrives late and costs the most when it does. The steel is designed, detailed, ordered and sometimes already primed before anyone confirms what fire rating it carries — and by then the primer on it may be the wrong primer.
It is worth understanding, because unlike most of the specification it is not the structural engineer's call.
What a fire resistance level actually is
A fire resistance level, or FRL, is written as three numbers in minutes, separated by slashes — structural adequacy, integrity, insulation. For a steel column or beam, usually only the first number applies, because a bare column is not asked to hold back smoke or heat the way a wall is.
The number comes from the National Construction Code and depends on the building's classification, its rise in storeys and its fire compartments. It is nominated by the fire engineer or the building certifier, not by the structural engineer and certainly not by the fabricator.
The practical consequence: a steel package can be fully designed and fully detailed and still have no fire information on it at all, because that information lives in a different consultant's documents.
The three ways steel gets protected
- Intumescent coating — applied like paint, swells into an insulating char when it gets hot. Thin, keeps the shape of the steel visible, and is the usual choice where the steel is on show.
- Board encasement — fire-rated board built around the member. Robust, hides the steel completely, and adds bulk that has to be allowed for in the architecture.
- Sprayed material — cementitious or vermiculite-based, sprayed on. Cheapest of the three and the least attractive, so it lives above ceilings and in plant rooms.
Which one is used is a decision that belongs to the architect and the fire engineer between them. It is not interchangeable at the fabricator's end, because each system wants a different surface underneath it.
Why it changes what happens in the workshop
Intumescent coatings only work over a compatible primer. Put a standard shop primer on a beam and then find out it needs intumescent, and that beam goes back through blasting before the coating system can start. That is not a touch-up — it is the whole member, again.
The thickness is calculated member by member, not applied at a blanket rate. A stocky column heats up slower than a light beam of the same rating, so it needs less protection. Detailers and applicators work from the section factor — how much heated surface a member has relative to how much steel there is to heat — which is why nobody can quote fire protection off a lump sum square metre rate until they have the schedule.
And there is the sequencing question. Shop-applied protection goes on in controlled conditions and comes out consistent, but it gets chipped by chains, slings and erection. Site-applied protection avoids that damage and instead needs access, dry weather and a clear work front. Neither is automatically right. Both need deciding early enough to plan around.
Where the money goes wrong
Three ways, in our experience.
The rating turns up after the steel is primed. Blasting and recoating, plus the programme time to do it.
The system changes after the architecture is set. Board encasement on a column that was drawn as an exposed 200 square section is suddenly a much larger column, and it fouls a door swing.
Nobody owns the touch-up. Shop-applied intumescent will pick up damage during erection. If the subcontract does not say who makes it good and to what standard, it becomes an argument at handover rather than a line item at tender.
What to have ready before the package is priced
- The FRL for each element, or written confirmation that no rating applies
- The named protection system, and whether it is shop or site applied
- The primer specification, confirmed compatible with that system
- Who applies it, and who repairs damage after erection
- What evidence is handed over — thickness readings, batch records, applicator certification
How we handle it
We ask the fire question at quote stage alongside the construction category and the coating system, because they are the same conversation. If a rating applies we price the surface preparation and primer to suit the named system, and we say plainly in the quote what we have assumed. If the answer is not available yet, the quote states what changes when it arrives — so the number is not quietly wrong.
Common questions
Does all structural steel need fire protection?
No. Plenty of structural steel carries no fire rating at all — external steel, open structures, and many low-rise buildings. Whether a rating applies comes from the National Construction Code for that building's classification and rise, and it is confirmed by the fire engineer or building certifier. Ask for it in writing either way, because an explicit nil is worth as much to a fabricator as a number.
Can fire protection be applied in the workshop instead of on site?
Often yes, and it usually comes out more consistent because conditions are controlled. The trade-off is damage: chains, slings and erection contact will mark a coated member, so shop application needs a site touch-up allowance and a clear agreement on who does it. Board and sprayed systems are more commonly applied on site.
Does the fabricator supply the fire protection?
Usually not. Intumescent, board and sprayed systems are applied by specialist applicators who are certified for the system they are installing. What the fabricator supplies is steel prepared to the surface standard that system requires, with a compatible primer, and the member schedule the applicator prices from.
What happens if the fire rating is confirmed after fabrication has started?
It depends how far along the steel is. Before priming, it is a change to the coating specification and little else. After priming with an incompatible product, affected members go back through blasting before the fire system can be applied, which costs both money and programme. It is the single strongest argument for settling the rating before the package is released.
Keep reading
More from the workshop
Durability
Galvanised, painted or duplex: choosing a steel finish in South East Queensland
Coating choice is a durability decision, not a colour decision — and the environment it sits in decides most of it.
Standards
Construction categories: CC1 to CC4, and which one your steel package needs
AS/NZS 5131 sorts structural steelwork into four construction categories. Naming the wrong one costs you either inspection you never needed, or paperwork that does not exist at handover.