Shop drawings: what has to be settled before anyone cuts steel
Shop drawings turn an engineer's design into the pieces a workshop actually makes. Four things hold them up every time, and all four are decided before fabrication starts.
In this article
The short answer
Shop drawings translate the engineer's design intent into the individual pieces a workshop cuts, drills and welds. Before detailing can start a fabricator needs the current issued-for-construction drawings, the connection design and who is responsible for it, the nominated finish, and a site dimension or set-out to work from. Approval turnaround is usually the longest single item on a steel programme, and the one nobody schedules.
An engineer's drawing shows a structure. A shop drawing shows a piece of steel: this length, these holes, that bevel, this mark number, welded here. Somebody has to do the translation, and until it is done and approved, nothing is cut.
That step is where most steel programmes quietly lose time — not because detailing is slow, but because the information it needs arrives in pieces.
The four things detailing waits on
1. Drawings that are actually current. Detailing from a superseded revision is the most expensive mistake available on a steel package, because it is not discovered in the office. It is discovered on site when a beam does not fit. Issued-for-construction drawings, with the revision clearly marked, are the only safe starting point — and if a revision lands mid-detailing, it needs to be sent through, not left in an inbox.
2. Connection design, and whose it is. Some engineers detail every connection. Some show a principle and leave it to the fabricator. Both are normal. What is not workable is silence — if nobody says, the fabricator either assumes and carries the risk, or stops and asks, and the programme takes the hit either way. Settle it before the package is priced: who designs the connections, who certifies them, and who pays for that engineering.
3. The finish. Galvanised steel needs vent and drain holes designed into the members, and they have to be on the shop drawings, not drilled as an afterthought. Painted steel needs the system named so the shop knows what surface preparation to allow. Changing the finish after detailing means re-detailing.
4. Something real to measure from. Steel is made to millimetres and concrete is not. Where new steel meets existing structure, a slab edge or a set of holding-down bolts already in the ground, a site dimension beats a drawing dimension every time. Agreeing early who takes that measure, and when, prevents a whole category of remake.
The approval loop, and how long to allow
Shop drawings go out for review, come back with comments, get revised, and go out again. Two rounds is normal. Three happens. Each round is real days, and those days sit on the critical path because fabrication cannot start without approval.
The lever a builder actually controls is turnaround. A package that sits with the engineer for a fortnight has moved the steel date by a fortnight, no matter how fast the workshop is. If the programme is tight, agree a review turnaround up front and put it in the subcontract alongside the fabrication period.
Revision control, in one rule
Every drawing carries a revision. Every transmittal names it. Nothing gets fabricated from an emailed PDF that does not say what revision it is. That single discipline removes more rework than any other habit on a steel job.
What you get back from us
- Shop drawings with mark numbers that match the erection drawing, so the crew on site can find the piece
- An erection drawing showing where each mark goes and in what sequence
- Connection details, with the design responsibility stated
- Vent and drain holes shown where the steel is being galvanised
- A clear list of anything we have assumed, so it can be corrected before it is cut rather than after
A short checklist before you issue a package
- Architectural, structural and services drawings at the same revision
- Connection design responsibility stated in writing
- Steel grades and any specified coating or finish system
- Construction category, if the project specifies one
- Site dimensions or set-out where steel meets existing work
- An agreed shop drawing review turnaround
- Delivery sequence, if the site needs the steel in a particular order
Common questions
What is the difference between a shop drawing and a structural drawing?
A structural drawing shows the designed structure and the loads it carries. A shop drawing shows one fabricated piece — its length, hole positions, cuts, welds and mark number — so a workshop can make it. One is design intent; the other is a set of manufacturing instructions.
Who is responsible for connection design on a steel package?
It depends on the project, which is exactly why it has to be stated. Some structural engineers design and detail every connection. Others nominate a principle and leave the fabricator to design connections to it, usually with a certifying engineer involved. Confirm it before pricing, because it changes both the price and who carries the risk.
How long does shop drawing approval usually take?
The drawing work itself depends on the size and complexity of the package. The review loop is what varies most, and it is driven by how quickly comments come back — not by the fabricator. Allow for at least two rounds and agree a review turnaround in the subcontract if the programme is tight.
Can you detail from an architect's drawings alone?
Not for structural steel. Architectural drawings set out geometry and finishes but not member sizes, grades or connections. Detailing needs the structural engineer's drawings, and where the two disagree, that disagreement has to be resolved before steel is cut.
Keep reading
More from the workshop
Standards
Construction categories: CC1 to CC4, and which one your steel package needs
AS/NZS 5131 sorts structural steelwork into four construction categories. Naming the wrong one costs you either inspection you never needed, or paperwork that does not exist at handover.
Programme
How long does structural steel fabrication actually take?
The honest answer is that it depends on the job — but the things it depends on are predictable, and most of them are decided before anyone cuts steel.