The week the steel arrives: what a builder should have ready
A steel package can be right in every dimension and still lose a week on site. What decides it is settled before the truck is booked, not on the morning it turns up.
In this article
The short answer
Four things decide whether a steel install runs: holding-down bolts surveyed and confirmed before the steel is loaded, a crane position and set-down area agreed in advance, truck access and a hardstand that will take the load, and a week where nobody else needs the same airspace. Everything else on erection day is recoverable. Those four are not.
Fabrication is measurable. Erection is a negotiation with a site. The steel arrives on a truck with a crane booked by the hour, and anything not ready that morning is paid for in crane time.
Most of what goes wrong is decided weeks earlier, and all of it is preventable.
1. Check the bolts before the steel is loaded
Holding-down bolts are cast into concrete by somebody else, often weeks before the steel exists. They move — during the pour, during the vibration, during the strip. A base plate drilled to the drawing and a bolt group set out to reality are the single most common reason a column does not go on.
The fix is a survey of the as-built bolt positions, checked against the shop drawings, before the steel leaves the workshop. If something has moved, there is still time to adjust a base plate in the shop with a drill press instead of on site with a grinder and an audience.
Grout, packers and levelling method are worth agreeing at the same time. They are small items that stop a crane.
2. Agree the crane position and the set-down area
Where the crane stands, what it can reach from there, and where the steel lands when it comes off the truck. A crane that has to be moved mid-lift because nobody checked a reach costs more than the extra hour it looks like.
Set-down matters as much. Steel dropped in the wrong order has to be re-handled, and re-handling is unpaid time on both sides. If the erection sequence needs the steel in a particular order, say so before it is loaded — trucks are packed last on, first off.
3. Truck access and ground that will carry it
Long members need room to turn, and a semi cannot reverse the length of a wet site. Gradient, overhead services, gate width, a hardstand that will take an outrigger, and whether the delivery window collides with someone else's concrete pour — all of it is a five-minute conversation that saves a day.
4. Book the airspace, not just the date
Erection needs the area clear, above as well as around. Scaffold going up the same wall, a concrete pump on the same slab, or another trade working underneath all stop the lift. Exclusion zones under a load are not negotiable, and the person who has to enforce them is on site that morning.
The things that follow the lift
Temporary bracing stays until the permanent structure is doing its job — the deck, the roof bracing, the shear connections. Removing it early because it is in someone's way is how a frame moves out of plumb, and frames that move out of plumb do not come back for free.
Then: bolting-up and tensioning where the connections are structural, any site welds with their procedure and coating repair planned rather than improvised, plumb and level checks, and touch-up on damaged coating before scaffold comes down and the steel becomes unreachable.
What we bring, and what we need from you
We install what we fabricate, with our own crew, which removes the handover gap where tolerances usually go missing — the people erecting it are the people who made it and know where the tight fits are.
What we need from the site, in writing before the truck is booked:
- Confirmed as-built set-out for holding-down bolts or fixing points
- An agreed crane position, reach and set-down area
- Delivery access, gate dimensions and a hardstand that takes the load
- Site induction requirements and timing, ahead of the day
- Which other trades are working in or above the zone that week
- Who signs off hold points, and when they will be on site
- Power and water availability where site welding is in scope
None of it is complicated. All of it is expensive when it is missing.
Common questions
Who is responsible for setting out holding-down bolts?
Normally the builder or the concreter, working from the engineer's set-out. The fabricator drills base plates to the shop drawings. Because the two are done by different parties at different times, the as-built positions should be surveyed and confirmed against the shop drawings before the steel leaves the workshop.
When can temporary bracing be removed?
Only once the permanent structure is capable of doing the job the bracing is doing — normally after the deck, roof bracing or permanent connections are complete. It is a question for the engineer, not a site decision, and removing it early is a common cause of frames going out of plumb.
Does the fabricator or the builder provide the crane?
Either, but it must be stated in the subcontract, because it is one of the larger single costs in an erection. Whoever books it, the crane position, reach and duration should be agreed with the erection crew in advance rather than assumed.
How much notice do you need before a steel delivery?
Enough to confirm the set-out, book transport and lifting, and complete site inductions — and enough to react if the survey shows something has moved. The exact lead time depends on the package; what matters is that the confirmation steps happen before the truck is loaded, not on the morning it arrives.
Keep reading
More from the workshop
Compliance
Stairs, balustrades and access platforms: the standards your steel has to meet
Steel stairs and barriers answer to more than one rulebook, and which one applies changes the geometry. It has to be settled before detailing, not at inspection.
Durability
Galvanised, painted or duplex: choosing a steel finish in South East Queensland
The finish is chosen from where the steel is going and how long it has to last — not from the price line. Here is how the decision is actually made, and what it does to your programme.